Natural gas connection and disconnection

ELECTRICITY EMERGENCY

13 10 93

GAS EMERGENCY

13 19 09

We own and operate two gas networks:

  1. The ACT Region network that services the ACT, Queanbeyan, Jerrabomberra, Googong and Bungendore
  2. The Nowra network that services Bomaderry and Nowra.

Jemena manages both gas networks for us, along with contractors, Zinfra, who maintain our infrastructure and provide field services.

Choose the right option for a gas connection, modification, or disconnection below.

Information about prices are on our gas network prices page, along with information about the ACT Region and Nowra gas networks.

How gas is supplied

Gas supplied through Evoenergy’s gas networks comes from:

  • APA Group’s Moomba-Sydney Pipeline System (MSP): sourced from on-shore gas fields in Queensland and South Australia
  • Jemena’s Eastern gas Pipeline (EGP): primarily sourced from off-shore fields in Victoria/Bass Strait.

All gas in Evoenergy’s networks conforms to Australian Standard AS 4564:2020 which specifies the characteristics of natural gas for general-purpose use.

  • Evoenergy does not currently blend either biomethane or hydrogen into natural gas it distributes
  • Evoenergy does not supply propane or LPG, which is transported and supplied in gas cylinders.

Arranging a new natural gas connection

New natural gas network connections are no longer available in the ACT unless your premises is exempt under the Regulation to prevent new gas connections in the ACT. Since 8 December 2023, new gas connections have been prevented in some zones and buildings under ACT Government regulation. These changes do not apply in NSW. More information is available on the ACT Government website.

There are two ways you can arrange a new eligible natural gas connection. You can choose to:

  1. Contact your energy retailer to arrange a new natural gas connection. Once your retailer submits a new natural gas connection application to us on your behalf, we will advise them within 10 business days if your connection is classified as either basic or negotiated. In the case of a basic connection, we will also provide your retailer with a connection offer.
  2. Use the Jemena connections portal to apply for a gas connection or modify or remove an existing one. You will still need to contact your energy retailer to sign up to or change your gas plan.

From 1 October 2026, an up-front connection charge will apply for all new connections under the National Rules.

Types of connections

Basic connection: a basic connection requires no extensions or modifications to the gas mains for an amount of up to 320MJ per hour (indicatively a cook-top, room heating and a hot water system). We do not charge for this service under our model standing offer for basic connection, however this will change from 1 October 2026 under National Rules.

Non-basic connection: a non-basic connection is available where the site requirements for a basic connection service are not satisfied. For example, if the property is on a major road or there are unusual site conditions.

Negotiated connection: all new connections over 320 MJ per hour or which require mains extension are classified as negotiated. Our Negotiation framework has more information.

Disconnections

  • Permanent disconnection (abolishment)

    If you want to switch your home from gas to electricity and no longer require natural gas at your premises – you should arrange a permanent disconnection, also known as an abolishment in the National Rules.

    "Permanent disconnection” and “abolishment” describe the same network service and are interchangeable. Evoenergy uses the term “Permanent Disconnection” as it is definitive and aligns with the ACT Policy to prevent future gas connections.

    A permanent disconnection must be arranged where building demolition works would be an unacceptable safety risk with gas present on the site.

    Contact your gas retailer in the first instance to arrange a permanent disconnection. Alternatively, you can submit an application through the Jemena connections portal.

    If you no longer want to use natural gas (all appliances are removed), permanent disconnection is the safest option as it:

    • Removes unused gas equipment from your property
    • Means your premises will no longer require maintenance, meter reading and routine checking of gas.

    Following a permanent disconnection:

    • The redundant service pipe will remain in the ground
    • The pipe will be purged of gas and physically disconnected from the distribution pipeline in the street at the front of your property.
    • The gas meter assembly will be removed.

    Basic permanent disconnection

    A basic permanent disconnection service applies to a single detached residential house where:

    • No cutting or restorations is required for concrete, bitumen and other hard surfaces
    • Active traffic management is not required.

    For properties with these restrictions or for more complex permanent disconnections, a negotiated complex permanent disconnection service is available. This may include:

    • High pressure connections
    • Large commercial or industrial sites and
    • multi-unit installations

    A basic permanent disconnection will be carried out in accordance with works planning and resourcing determined by our field sub-contractor, Zinfra.

    If you require the permanent disconnection completed by a particular date, such as before demolition works start, an urgent basic permanent disconnection service is available where the permanent disconnection will be carried out within 20 business days of the application.

    Pricing

    • Basic permanent disconnection: $747 (excl. GST) for a residential gas meter up to and including 25 cubic metres per hour capacity. (A standard residential gas meter has a capacity of 8 cubic metres per hour)
    • Set charges for larger gas meters. See the gas network prices on our website.
    • Your gas retailer may charge a higher amount when passing on Evoenergy’s charge.
    • Urgent basic permanent disconnection: $981 (excl. GST) charged by Evoenergy.

    Indicative timeframe

    Urgent basic permanent disconnection

    Completed within 20 business days of the application.

    Basic permanent disconnection (non-urgent)

    Completed in accordance with Zinfra’s works planning and resourcing, typically within 6 months of application.

    A Basic permanent disconnection includes:

    • Tracing of the service pipe from meter to the gas main.
    • Excavation to expose the service pipe near the gas main.
    • Cut and cap the service pipe in the public verge, near the gas main.
    • Reinstate soil and compact. Replace any grass sods previously removed.
    • Cut gas riser at ground level near the meter.
    • Remove the metering equipment.
  • Complex permanent disconnection

    Complex permanent disconnections covers all permanent disconnections that are not Basic (whether urgent or non-urgent) and are individually priced depending on the scope of work.

    Typical work scopes include:

    • Concrete cutting and restoration;
    • Active traffic management;
    • High pressure connections,
    • Large commercial or industrial sites; and
    • Multi-unit sites where coordination between multiple unit-holders and the ownership committee, strata title manager etc. is required.
  • Temporary disconnection

    A temporary disconnection is appropriate if you intend to reconnect your gas supply in the future.

    Following a temporary disconnection:

    • Gas remains within the distribution pipeline at your property
    • Your gas supply can be restored through a reconnection request

    Price: $100 (ex GST) for a temporary disconnection and $128 (ex GST) for a reconnection of a standard residential gas meter.

    Indicative timeframe

    • Evoenergy aims to complete 95% of temporary disconnections within 5 business days from receiving the retailer’s work order.
    • National Rules regarding how work is to be carried out for Fridays and days before public holidays apply.

    Arranging a temporary disconnection

    A temporary disconnection can be arranged through your energy retailer if you need to disconnect from gas for a short period. This method should only be used if:

    • you plan to reconnect gas in the future; or
    • you continue to protect the pressurised service pipe and metering equipment on your premises.

    A temporary disconnection includes

    To complete a temporary disconnection, a technician will modify the internals of a gas meter, preventing gas from flowing through the meter. Once completed, this cannot be seen from the outside of the meter and needs special skills to reverse.

    A temporary disconnection also prevents gas from entering a building. However, there is still pressurised gas in the service pipe connecting the network to the gas meter assembly. This means there remains a risk of damage to the service pipe if excavation activity comes in contact with it.

Which service do I need?

Choose a temporary disconnection if you:

  • Only need your gas supply disconnected for a short period
  • Intend to reconnect your gas supply in the future

You can also choose a temporary disconnection where you do not intend to use gas again if you continue to protect the service pipe and meter installation from damage. This may be required for many years until the network itself is decommissioned (and depressurised) in your neighbourhood.

Choose a permanent disconnection (abolishment) if you:

  • Are demolishing your property
  • No longer require a gas connection
  • Want to remove the requirement to protect the service pipe and meter installation from future damage

Your rights and obligations

When requesting a temporary or permanent gas disconnection:

  • Provide complete and accurate information with your application
  • Ensure the service requested is appropriate for your circumstances
  • Evoenergy will complete the requested service in accordance with applicable energy laws and technical requirements.

If you have a complaint about our services, please see our Complaints and feedback page for information on how to lodge a complaint and the options available if you’re not satisfied with the outcome.

Other applications and requirements

Application for connection of detached residential premises
Connection of residential premises terms and conditions
Non-basic residential connection terms and conditions
Application for natural gas meter relocation
Natural gas meter relocation terms and conditions
Natural gas meter location guide
Application for meter/service upgrade or downgrade
Connection alteration (meter upgrade or downgrade) terms and conditions
Application for decommissioning and meter removal
Decommissioning and meter removal terms and conditions
Application for pulse output connection
Pulse output connection terms and conditions
Application for medium density/high rise connection
Medium density/high rise terms and conditions
Application for connection to new industrial or commercial development
Connection to new industrial or commercial development terms and conditions
Model standing offer for basic connection services – Gas
Requirements for gas centralised hot water system