MENU

Electricity emergency

Gas emergency

Evoenergy is continually planning for the future and securing the ACT and region's energy supplies.

Gold Creek Substation

Evoenergy is finalising Capital Works initiated in August 2018 to provide a new feeder from Gold Creek Zone Substation in Amaroo to the Canberra Metro Traction Power Station along Flemington road. This work is essential to ensure we continue to provide a reliable supply to Canberra Metro Light Rail and to the growing Gungahlin Town Centre. One supply to Canberra Metro Light Rail from Hamer street to Flemington Road was successfully terminated and energised mid-November. Civils works to enable the cable feeder to be installed for the second supply progressed along Hinder street and has resumed at the corner of Gozzard St and Anthony Rolfe. The works are due for completion by Christmas 2018.

Lawson South Stage 2

Following a number of changes to the ACT Government Land Development Agency’s (LDA) development strategy for Lawson South Stage 2, Evoenergy is commencing detailed design work for the requisite undergrounding of both 132kV transmission lines and 11kV distribution lines around the Belconnen zone substation. Noting the variation to previously agreed works, we will continue to work with the LDA to support their new approach to market.

Molonglo zone substation

At Evoenergy, we understand the ongoing energy needs of the community. That’s why we intend to construct a new 132/11kV zone substation in Molonglo, so we’re ready to meet the electricity needs of the Molonglo Valley, in the future.

The substation will provide an additional 55MVA capacity, enough to supply more than 20,000 homes with electricity.

Molonglo Stage 1 - land acquisition and development application (DA) approval is underway, with completion of the Stage 1 construction in the next four to five years.

Optical Fibre replacement project

Evoenergy is installing optical fibre communications between our zone substations to improve system reliability and security standards. Five optical fibre wires have been installed, with one further cable still to be completed. This project involves replacing existing wires with new aluminium ones that contain optical fibre cores through the middle of the conductors on top of the towers.

As our network grows and customer base expands these security upgrades will allow us to get more out of existing assets, reduce costs and provide opportunities to diversify the grid. The works will also ensure we continue to meet reliability and security standards as set by the Australian Energy Market Operator (AEMO). The second stage is in progress, with remaining stages due for completion by the middle of 2018.

Secondary electricity supply for the ACT

Having a second point of electricity supply into the ACT will supplement the existing major electricity supply point in northern Canberra and is an important part of ensuring a reliable and secure electricity supply to the ACT.

The first stage of the second point of supply to the ACT project involved the construction by TransGrid in 2013 of the 330/132 kV Williamsdale Substation in the south of the ACT. This substation has been connected to Evoenergy's network via two new 132 kV transmission lines to Evoenergy's Theodore and Gilmore substations.

To complete the second point of supply to the ACT project, the following works are proposed and will be completed by 2020:

Construction of a new 330/132 kV substation by TransGrid at Stockdill Drive, West Belconnen.
Construction by TransGrid of a new 330 kV transmission line from Stockdill Substation to Canberra Substation.
Reconnection by TransGrid of its 330 kV Upper Tumut - Canberra transmission line to Upper Tumut - Stockdill.
Reconnection by TransGrid of its 330 kV Canberra - Williamsdale transmission line to Stockdill - Williamsdale.
Construction by Evoenergy of a new 132 kV transmission line from Stockdill Substation to connect to its Canberra - Woden transmission line.

Subject to environmental approval, construction work will commence in the second half of 2018. Further information on this project can be found here or on the TransGrid website.

Transmission Network Service Provider TNSP

To accurately record network losses, and in compliance with regulatory requirements on metering, Evoenergy is adding metering at each zone substation.

Loading power...